Park Blvd

Park Boulevard
The limits of the project are from Roosevelt Road to Crescent Boulevard. The improvements include pavement reconstruction from Roosevelt Road to Fairview Avenue and pavement rehabilitation from Fairview Avenue to Crescent Boulevard. Included in the above work is earth excavation, placement of aggregate subgrade, combination concrete curb and gutter, hot-mix asphalt pavement, portland cement concrete sidewalk, storm sewer, sanitary sewer repairs, water main installation, pavement markings, traffic staging, temporary detour, restoration, and all other appurtenant work required to complete the project.

Main Street

Main Street
The limits of the project are from Roosevelt Road to Fairview Avenue. The improvements include pavement rehabilitation, earth excavation, placement of aggregate subgrade, combination concrete curb and gutter, hot-mix asphalt pavement, portland cement concrete sidewalk, storm and sanitary sewer structure adjustments, pavement markings, restoration, and all other appurtenant work required to complete the project.

Start Date

Anticipated Start Date:
Main Street: April 30, 2018; dependent on weather.
Park Boulevard: June 11, 2018; dependent on weather and utility relocation work.

Saturday, July 21, 2018

Park Blvd. - Fairview Ave. to Crescent Blvd. - HMA Surface


Abari Construction will complete adjusting the storm, sanitary and water main structures by Tuesday, July 24th. Once this is completed, Dunteman Construction will place bituminous prime coat on the roadway. Prime signs will be erected prior to this work being performed. Currently, Dunteman Construction plans on placing the hot-mix asphalt surface course on Thursday, July 26th and Friday, July 27th if weather allows.