The limits of the project are from Roosevelt Road to Crescent Boulevard. The improvements include pavement reconstruction from Roosevelt Road to Fairview Avenue and pavement rehabilitation from Fairview Avenue to Crescent Boulevard. Included in the above work is earth excavation, placement of aggregate subgrade, combination concrete curb and gutter, hot-mix asphalt pavement, portland cement concrete sidewalk, storm sewer, sanitary sewer repairs, water main installation, pavement markings, traffic staging, temporary detour, restoration, and all other appurtenant work required to complete the project.

Main Street

Main Street
The limits of the project are from Roosevelt Road to Fairview Avenue. The improvements include pavement rehabilitation, earth excavation, placement of aggregate subgrade, combination concrete curb and gutter, hot-mix asphalt pavement, portland cement concrete sidewalk, storm and sanitary sewer structure adjustments, pavement markings, restoration, and all other appurtenant work required to complete the project.

Start Date

Anticipated Start Date:
Main Street: April 30, 2018; dependent on weather.
Park Boulevard: June 11, 2018; dependent on weather and utility relocation work.

Saturday, July 21, 2018

Park Blvd. - Fairview Ave. to Crescent Blvd. - HMA Surface


Abari Construction will complete adjusting the storm, sanitary and water main structures by Tuesday, July 24th. Once this is completed, Dunteman Construction will place bituminous prime coat on the roadway. Prime signs will be erected prior to this work being performed. Currently, Dunteman Construction plans on placing the hot-mix asphalt surface course on Thursday, July 26th and Friday, July 27th if weather allows.

Park Blvd. - Roosevelt Rd. to Fairview Ave. - Sanitary Sewer


Abari Construction will begin underground work on Monday, July 23rd.  They will begin with repairing sanitary sewer main that is currently deficient.

Wednesday, July 11, 2018

Park Boulevard Paving Schedule - Fairview to Crescent

The Contractor intends to complete all work, except parkway sodding, on Park Boulevard from Fairview to Crescent by Friday, August 3.  The narrative below lays out the tentative and weather dependent schedule.

Paving of Leveling Binder Layer of Asphalt - Friday, July 13
The Contractor intends to pave the first one-inch (1") thick layer of asphalt on Park Boulevard from Fairview to Crescent Boulevard on Friday, July 13.  This layer of asphalt establishes a smooth and properly sloped base to pave the final surface layer of asphalt on, prevents the reflection of cracks in the underlying concrete base through the final surface layer of asphalt, and provides a reference point for the proper re-installation of the manhole frames/covers to the correct grade in the roadway.  Prior to this paving operation, the Contractor will sweep and prime the roadway with oil (on Thursday, July 12).

Re-installation of Manhole Frames/Covers - Week of July 16 - Week of July 23
It is anticipated that all the manhole frames/covers will be re-installed in the roadway starting the week of July 16.  This process involves breaking out the asphalt pavement around each structure in the roadway, removing the temporary plate underneath, setting the manhole frame/cover on new adjusting rings over the structure, and pouring concrete around the manhole frame.  The frames/covers will be reinstalled in phases to avoid a complete closure of Park Boulevard.  As such, the work will take approximately one week to complete including curing of the concrete around the manhole frames.

Paving of Surface Layer of Asphalt - Week of July 23
Weather permitting, the Contractor intends to pave the second and final two-inch (2") thick layer of asphalt on Park Boulevard from Fairview to Crescent during the week of July 23.  The tentative date of surface paving is Tuesday, July 24.  Please understand this date is subject to change given the timing of this notice.  Prior to this paving operation, the Contractor will sweep and prime the roadway with oil.

Other various activities to be completed by August 3 include: two storm sewer repairs, a water main valve replacement, concrete curb placement for sidewalk ramps, rough grading/backfill of voids along the curbs and sidewalks, asphalt driveway patching adjacent to sidewalk replacement, and restoration of pavement markings.

Residents should anticipate these work activities to cause temporary roadway lane and driveway closures as well as general delays and inconveniences in driving through the project corridor.

Thursday, July 5, 2018

Park Boulevard Update 7/5/2018

Park-Hill Intersection Reconstruction
The Contractor completed the placement of the concrete roadway pavement on Tuesday, July 3.  The intersection will be-reopened to vehicular traffic on Monday, July 9.  Construction of the sidewalk ramps will be completed following adjustment of the phone duct manholes (at the southeast and southwest quadrants of the intersection) by AT&T's Contractor.






Park Boulevard from Roosevelt to Fairview
Following the opening of the Park-Hill Intersection to vehicular traffic, the Contractor will implement a one-way northbound only traffic configuration on Park Boulevard from Roosevelt to Fairview.  The utility and roadway reconstruction work will commence immediately thereafter.  Please see the images below for further details including an exhibit.





Park Boulevard from Fairview to Crescent Boulevard
Milling (removal) of the asphalt roadway pavement is underway.  Next steps will include completion of two storm sewer point repairs, patching of the roadway base where necessary, paving of the asphalt roadway binder layer, re-installation of the manholes, paving of the asphalt roadway surface course, pavement markings, and parkway lawn restoration.