Construction Update - October 31, 2018
Please be advised that the
Contractor has notified residents on Park between Maiden and Fairview to refrain from the use of their driveway
until the new curbs, driveway approaches, sidewalks, and first two layers of
asphalt paving are complete and sufficient for use. The tentative schedule for this work is as
follows:
Thursday, Nov. 1 – Roadway will be graded for curb installation
Friday, Nov. 2 – Curb will be installed on Park from Maiden
to Fairview
Monday, Nov. 5 – Wednesday, November 7 – Driveways will be
excavated, stoned, and poured.
Thursday, Nov. 8 and Friday Nov. 9 – First two layers of
asphalt will be paved
Monday, Nov. 12 – Driveways will be re-opened for use by
residents
Please legally park your
vehicles on adjacent side streets that are not under construction such as
DuPage, Exmoor, Summerdale, and Stephanie.
Please abide by the no parking signs, face your vehicle in the correct
direction of traffic, and do not block fire hydrants and driveways. The Police Department has been notified to
not ticket vehicles that are parked overnight on side streets in the area, so
long as they are parked legally otherwise.
Weather permitting, the
remaining work including restoration of parkways, paving of the asphalt surface
course, and pavement markings is currently anticipated to be completed by Nov.
21. However, the contractor is striving
to complete the work sooner, as possible.