The limits of the project are from Roosevelt Road to Crescent Boulevard. The improvements include pavement reconstruction from Roosevelt Road to Fairview Avenue and pavement rehabilitation from Fairview Avenue to Crescent Boulevard. Included in the above work is earth excavation, placement of aggregate subgrade, combination concrete curb and gutter, hot-mix asphalt pavement, portland cement concrete sidewalk, storm sewer, sanitary sewer repairs, water main installation, pavement markings, traffic staging, temporary detour, restoration, and all other appurtenant work required to complete the project.

Main Street

Main Street
The limits of the project are from Roosevelt Road to Fairview Avenue. The improvements include pavement rehabilitation, earth excavation, placement of aggregate subgrade, combination concrete curb and gutter, hot-mix asphalt pavement, portland cement concrete sidewalk, storm and sanitary sewer structure adjustments, pavement markings, restoration, and all other appurtenant work required to complete the project.

Start Date

Anticipated Start Date:
Main Street: April 30, 2018; dependent on weather.
Park Boulevard: June 11, 2018; dependent on weather and utility relocation work.

Wednesday, June 20, 2018

Main Street and Park Boulevard Progress Update

Main Street (Roosevelt to Fairview) - The work is substantially complete with a few remaining punch list items including the installation of a parkway drain, curb patch, and cleaning of the street drainage structures.  As a reminder, the Illinois Department of Transportation will be resurfacing the balance of the intersection of Main and Roosevelt this summer as part of its Roosevelt Road resurfacing project.

Park Boulevard (Roosevelt to Fairview) - Nicor is nearly complete with its utility relocation work being performed as part of the project.  It is tentatively anticipated that the one-way northbound only traffic configuration through this corridor of Park Boulevard will be implemented on Monday, July 9. Changeable Message Signs will be installed (on Park) one week in advance of the traffic configuration change to notify the motoring Public.  Commencement of the sewer/water utility and roadway work will immediately follow the implementation of the one-way traffic control plan.

Park Boulevard (Fairview to Crescent) - Completion of the spot curb/gutter and sidewalk removal and replacement work is anticipated by the week of June 25.  Cleanup of the work area including barricade removal and backfilling along sidewalks and curbs is also anticipated to be completed the week of June 25.  The underground contractor is in the process of removing the manhole frames/covers in the roadway.  This operation facilitates more efficient milling (removal) of the asphalt pavement.

Park/Hill Intersection - Reconstruction of the Park/Hill intersection is underway.  All roadway pavement in the intersection has been removed with the contractor currently focusing on excavation, construction of the stone sub-grade and sub-base, and fine grading of the intersection prior to concrete paving.