A summary of recently
completed and forthcoming activities by location is as follows:
Main Street (Roosevelt to Fairview): Work is substantially complete. As a reminder, the Illinois Department of
Transportation will be resurfacing the balance of the intersection of Main and
Roosevelt this summer/fall as part of its Roosevelt Road resurfacing project.
Park Boulevard (Fairview to Crescent): Work is substantially complete with the exception of
parkway lawn restoration which will be completed in the fall.
Park Boulevard (Roosevelt to Fairview): The Contractor has completed the planned sanitary
sewer service replacement work.
Installation of the new water main has commenced with the contractor
starting work from the south leg of the Park and Fairview intersection and
heading south towards Roosevelt Road.
Once the new water main
has been installed, it will be pressure tested, chlorinated, and sampled in
accordance with all IEPA requirements prior to putting it into service. The Contractor will then begin installing new
water services to connect properties to the new water main.
Additional utility work to
be completed on the east half of Park Boulevard includes replacement of a
section of sanitary sewer main at the intersection of Fairview and Park, and
installation of new storm sewer and drainage structures along the project
corridor.
Once the utility work on
the east half of the Park Boulevard is complete, the contractor will commence
construction of the east half of the roadway.
This work will involve construction of a new stone roadway sub-grade,
installation of new curbs, replacement of driveway approaches and sidewalks,
and paving of the roadway with asphalt to a level approximately 2-inches below
the final roadway surface elevation. The
final 2-inch surface layer of asphalt will be paved towards the end of the
project along with the west half of the roadway.
Upon construction of the
east half of the roadway as described, it will be used for northbound traffic. The Contractor will then commence
construction of the utility improvements and roadway on the west half of Park
Boulevard. This work should progress
more quickly given the majority of the utility work is being completed on the
east half of the roadway.