Main Street (Roosevelt to Fairview) Progress Update
Pavement milling on Main Street (Roosevelt to Fairview) including the removal of approximately 3-inches of the asphalt roadway pavement was completed on Thursday, May 17. Inspection of the asphalt pavement base by Resident Engineer Flodstrom and Professional Engineer Daubert concluded that the pavement base is in good condition with only one location identified for patching. Patching work was completed on Friday, May 18.
Weather permitting, the Contractor will prime the milled pavement base on Monday, May 21, pave the first 1-inch thick layer of asphalt on Tuesday, May 22, re-install the manhole frames/covers in the roadway on Wednesday, May 23 and pour the balance of the concrete curb, driveway, and sidewalk pavement.
The concrete around the manhole frames/covers will need to cure through the Memorial Holiday Weekend. Paving of the second and final layer (2-1/4-inches) of asphalt will be completed after the Holiday Weekend when the concrete has sufficiently cured.