Park Blvd

Park Boulevard
The limits of the project are from Roosevelt Road to Crescent Boulevard. The improvements include pavement reconstruction from Roosevelt Road to Fairview Avenue and pavement rehabilitation from Fairview Avenue to Crescent Boulevard. Included in the above work is earth excavation, placement of aggregate subgrade, combination concrete curb and gutter, hot-mix asphalt pavement, portland cement concrete sidewalk, storm sewer, sanitary sewer repairs, water main installation, pavement markings, traffic staging, temporary detour, restoration, and all other appurtenant work required to complete the project.

Main Street

Main Street
The limits of the project are from Roosevelt Road to Fairview Avenue. The improvements include pavement rehabilitation, earth excavation, placement of aggregate subgrade, combination concrete curb and gutter, hot-mix asphalt pavement, portland cement concrete sidewalk, storm and sanitary sewer structure adjustments, pavement markings, restoration, and all other appurtenant work required to complete the project.

Start Date

Anticipated Start Date:
Main Street: April 30, 2018; dependent on weather.
Park Boulevard: June 11, 2018; dependent on weather and utility relocation work.

Thursday, July 5, 2018

Park Boulevard Update 7/5/2018

Park-Hill Intersection Reconstruction
The Contractor completed the placement of the concrete roadway pavement on Tuesday, July 3.  The intersection will be-reopened to vehicular traffic on Monday, July 9.  Construction of the sidewalk ramps will be completed following adjustment of the phone duct manholes (at the southeast and southwest quadrants of the intersection) by AT&T's Contractor.






Park Boulevard from Roosevelt to Fairview
Following the opening of the Park-Hill Intersection to vehicular traffic, the Contractor will implement a one-way northbound only traffic configuration on Park Boulevard from Roosevelt to Fairview.  The utility and roadway reconstruction work will commence immediately thereafter.  Please see the images below for further details including an exhibit.





Park Boulevard from Fairview to Crescent Boulevard
Milling (removal) of the asphalt roadway pavement is underway.  Next steps will include completion of two storm sewer point repairs, patching of the roadway base where necessary, paving of the asphalt roadway binder layer, re-installation of the manholes, paving of the asphalt roadway surface course, pavement markings, and parkway lawn restoration. 