Park Blvd

Park Boulevard
The limits of the project are from Roosevelt Road to Crescent Boulevard. The improvements include pavement reconstruction from Roosevelt Road to Fairview Avenue and pavement rehabilitation from Fairview Avenue to Crescent Boulevard. Included in the above work is earth excavation, placement of aggregate subgrade, combination concrete curb and gutter, hot-mix asphalt pavement, portland cement concrete sidewalk, storm sewer, sanitary sewer repairs, water main installation, pavement markings, traffic staging, temporary detour, restoration, and all other appurtenant work required to complete the project.

Main Street

Main Street
The limits of the project are from Roosevelt Road to Fairview Avenue. The improvements include pavement rehabilitation, earth excavation, placement of aggregate subgrade, combination concrete curb and gutter, hot-mix asphalt pavement, portland cement concrete sidewalk, storm and sanitary sewer structure adjustments, pavement markings, restoration, and all other appurtenant work required to complete the project.

Start Date

Anticipated Start Date:
Main Street: April 30, 2018; dependent on weather.
Park Boulevard: June 11, 2018; dependent on weather and utility relocation work.

Tuesday, November 20, 2018

Construction Update November 20, 2018

All concrete sidewalk and driveway pavement replacement work has been substantially completed with the exception of any punch list items of work.  Paving of the asphalt surface course was completed on Friday, November 16 with the roadway pavement markings completed on Tuesday, November 20.  

The contractor is currently focusing on cleaning up the work site as well as excavating and placing topsoil in the parkways.  Sodding of the parkways is anticipated to be completed over the next week.  A preliminary punch list has been provided to the contractor with those items to be completed by the contractor in the next two weeks.

Park Boulevard will be re-opened to two-way traffic by 4 p.m. on Wednesday, November 21 (tomorrow).  Daytime lane closures and detours will be required and utilized to complete some of the previously noted remaining items of work.


No comments:

Post a Comment