The contractor is currently focusing on cleaning up the work site as well as excavating and placing topsoil in the parkways. Sodding of the parkways is anticipated to be completed over the next week. A preliminary punch list has been provided to the contractor with those items to be completed by the contractor in the next two weeks.
Park Boulevard will be re-opened to two-way traffic by 4 p.m. on Wednesday, November 21 (tomorrow). Daytime lane closures and detours will be required and utilized to complete some of the previously noted remaining items of work.