Construction Update - October 24, 2018
The Public Works team
would like to update you regarding the status of the project. Given that the resurfacing work on Main
Street from Roosevelt to Fairview and on Park Boulevard from Fairview to
Crescent is substantially complete, this notice will focus on providing an
update for the section of Park under reconstruction between Roosevelt and
Fairview.
Utility Work
The underground contractor
has completed the installation of all water services and is in the process of
completing the final connections of the new water main to the existing water
distribution system. The underground contractor
is also wrapping up the storm sewer installation work including installation of
structures that were in conflict with the old water main as well as installing
underdrain pipes. It is currently
anticipated that the underground utility work will be substantially complete by
Saturday, October 27.
Roadway Work
The general contractor is
in the process of constructing the new aggregate base for the roadway. Concurrent with this operation, the
contractor will commence construction of the new concrete curb/gutter and concrete
driveway approaches.
At the time of this
notice, the general contractor is wrapping up the roadway base construction
effort on the south half of Park between Maiden and Roosevelt. This work has also advanced to the north with
the aggregate base construction on the section of Park from Fairview to Maiden
having commenced on Tuesday, October 23.
It is anticipated that the contractor will start constructing the new
curb and driveway approaches on the south end of Park on Friday, October
26. Construction of the new curb and
driveway approaches on the northern end of Park between Maiden and Fairview is
anticipated to commence on Thursday, November 1. A separate notice will be provided to those
residences losing driveway access (Starting Around November 1). At that time, residents should anticipate to
be out of their driveways for approximately 10-14 days while the new concrete
curb and driveway approaches are constructed and curing to sufficient
strength. During this same driveway closure
period, the contractor will be paving the roadway to an elevation approximately
2-inches below the final surface elevation of the street, thereby allowing
driveway access to be restored shortly thereafter. Weather permitting, it is currently anticipated
that this work will be complete by approximately November 9 with driveways
re-opened by November 12.
Weather permitting, it is
currently anticipated that the final 2-inch thick asphalt surface layer of the
roadway will be paved and line-striped by approximately November 16 with the
roadway re-opened to two-way traffic at that time. Restoration of disturbed lawn areas will be
completed as weather and the availability of sod permits.
We would like to take a
moment to sincerely thank you for your patience and cooperation throughout the
conduct of this project. We are looking
forward to completing the final phases of work and delivering another quality
infrastructure improvement project to the Village of Glen Ellyn.
A copy of the notification letter containing this same information is provided below.