Park Blvd

Park Boulevard
The limits of the project are from Roosevelt Road to Crescent Boulevard. The improvements include pavement reconstruction from Roosevelt Road to Fairview Avenue and pavement rehabilitation from Fairview Avenue to Crescent Boulevard. Included in the above work is earth excavation, placement of aggregate subgrade, combination concrete curb and gutter, hot-mix asphalt pavement, portland cement concrete sidewalk, storm sewer, sanitary sewer repairs, water main installation, pavement markings, traffic staging, temporary detour, restoration, and all other appurtenant work required to complete the project.

Main Street

Main Street
The limits of the project are from Roosevelt Road to Fairview Avenue. The improvements include pavement rehabilitation, earth excavation, placement of aggregate subgrade, combination concrete curb and gutter, hot-mix asphalt pavement, portland cement concrete sidewalk, storm and sanitary sewer structure adjustments, pavement markings, restoration, and all other appurtenant work required to complete the project.

Start Date

Anticipated Start Date:
Main Street: April 30, 2018; dependent on weather.
Park Boulevard: June 11, 2018; dependent on weather and utility relocation work.

Thursday, August 30, 2018

Park and Fairview Intersection Detours for Sewer and Water Work


Sanitary Sewer Work
Starting on Tuesday, September 4 and extending through Thursday, September 6, the underground contractor will be replacing a section of sanitary sewer main in the east half of the intersection of Park and Fairview.  The detour route pictured below will be implemented on these days with the detour anticipated to be knocked down, and intersection restored to its current traffic control state (all movements permitted except southbound Park) at the end of the working day on Thursday, September 6.

Water Main Work
Starting on Monday, September 10 and extending through Friday, September 14, the underground contractor will be replacing the water main within the intersection of Park and Fairview.  This work will require implementation of the same detour route with some additional daytime modifications as the contractor digs across the various legs of the intersection.  It is anticipated that the detour will be knocked down, and intersection restored to its current traffic control state (all movements permitted except southbound Park) at the end of the working day on Friday, September 14.

Please understand that the above dates are subject to change due to weather delays and/or construction conflicts.  The detour route may also be modified during construction to allow for the work to be safely performed.





 