Park Blvd

Park Boulevard
The limits of the project are from Roosevelt Road to Crescent Boulevard. The improvements include pavement reconstruction from Roosevelt Road to Fairview Avenue and pavement rehabilitation from Fairview Avenue to Crescent Boulevard. Included in the above work is earth excavation, placement of aggregate subgrade, combination concrete curb and gutter, hot-mix asphalt pavement, portland cement concrete sidewalk, storm sewer, sanitary sewer repairs, water main installation, pavement markings, traffic staging, temporary detour, restoration, and all other appurtenant work required to complete the project.

Main Street

Main Street
The limits of the project are from Roosevelt Road to Fairview Avenue. The improvements include pavement rehabilitation, earth excavation, placement of aggregate subgrade, combination concrete curb and gutter, hot-mix asphalt pavement, portland cement concrete sidewalk, storm and sanitary sewer structure adjustments, pavement markings, restoration, and all other appurtenant work required to complete the project.

Start Date

Anticipated Start Date:
Main Street: April 30, 2018; dependent on weather.
Park Boulevard: June 11, 2018; dependent on weather and utility relocation work.

Sunday, May 6, 2018

Main St. Construction Begins


Roadway construction work began along Main Street on Tuesday, May 1st.  R.W. Dunteman started removing concrete sidewalk and curb & gutter from Roosevelt Rd. to Fairview Ave. Starting the week of May 6th, storm and sanitary sewer frames and grates located in the curb line will be replaced with new frame and grates.  Once this work is completed, new concrete curb & gutter will poured.  While this work is occurring, Main St. traffic will be reduced to one-way traffic at times.  Flag workers will be utilized to control traffic.  Please drive slowly and carefully through the construction zone.  Thank you. 